Keep up to date
Register to receive the latest project information and announcements including updates and opportunities to get involved.
-
Planning
Planning for the Hunter Transmission Project is well underway in line with the planning approval pathway for critical State significant infrastructure.
To learn more about planning approvals and the EIS, visit environmental impact statement for the Hunter Transmission Project.
-
Under construction
If the Hunter Transmission Project is approved, construction is expected to start in 2027. Construction will be staged to help manage environmental and community impacts.
-
Operational
Once operational, the Hunter Transmission Project will help deliver clean, reliable energy across NSW.
Supporting infrastructure
We’ll build 2 new switching stations – 1 near the existing Bayswater substation and another at a former timber plantation site in Olney State Forest.
Switching stations are facilities that contain high-voltage equipment used to connect different parts of the electricity network and help manage how power flows. We need the 2 new switching stations to connect the new transmission line to the existing 500 kV network.
Each site will include high-voltage switchgear, control buildings and associated infrastructure, with a short overhead line connecting the switching stations to the main transmission line.
We considered a range of factors when selecting the location for the new switching stations, including proximity to the existing network, access, network performance, and minimisation of environmental and land use impacts.
Upgrades at the existing substations at the Bayswater and Eraring power stations will be needed to connect the HTP to the electricity network.
All upgrades will take place within the existing substation sites, so no extra land or vegetation clearing will be needed.
At Bayswater, we’ll connect the new Bayswater South switching station with a short one-kilometre double circuit line, install two new switchbays (which help control how power flows through the substation), and expand the substation footprint to fit new equipment.
At Eraring, we’ll install new landing spans (short overhead lines connecting the transmission line into the substation), upgrade some existing equipment so it can handle more load, relocate or upgrade switchgear, and add new transformer units and associated equipment.
These upgrades won’t change how the substations operate and there will be no increase in operational noise or electromagnetic fields (EMF).
If the Hunter Transmission Project is approved, some public roads, intersections and access tracks will need to be upgraded, and in some cases new access tracks will need to be built.
This will occur in places where they simply aren’t wide enough or suitable for large trucks carrying oversize loads of construction equipment, plant machinery and the transmission towers.
Access roads and tracks will also be needed for maintenance when the new transmission infrastructure is operational.
We’ll consult with Transport for NSW and local councils through detailed design and construction to ensure safety and minimise disruptions.
Read more in our traffic and transport impact assessment fact sheet (September 2025).
We’ll build temporary construction support sites to house workers, store materials and stage the transport of equipment for the HTP.
Five temporary support sites are proposed at Muswellbrook, Millfield, Howick, Gouldsville and Cooranbong. Three of these sites would include temporary workforce accommodation, with space for around 780 workers.
The sites will serve as bases for construction activities and could include facilities and amenities such as kitchens and recreation areas, demountable offices, and areas for storing equipment, materials, chemicals and gas.
We’ll also set up temporary laydown areas along the transmission line route to support flexible construction staging. These areas will be used for stockpiling materials, setting up equipment, managing traffic, and helping to reduce vehicle movements to and from the main compounds. Laydown areas are generally located where more accessible and less accessible construction zones meet.
Read more in our temporary construction support sites fact sheet (September 2025).
To support the construction of the Hunter Transmission Project we’ll need to make adjustments to some existing 330 kV and 500 kV transmission lines operated by Transgrid, along with some lower voltage lines operated by Ausgrid and mining infrastructure owners.
We’ll also upgrade overhead earth wires and install new communications systems on a number of existing 500 kV transmission lines operated by Transgrid. These upgrades help protect the network from lightning strikes and improve monitoring to quickly detect faults.
Where possible this work will occur within existing easements to minimise impacts.
Who will build the project?
A network operator will be appointed and take responsibility for the construction and operation of the transmission line. They’ll also be responsible for managing the construction contractors.
There will be two main contractors – one to build the transmission line and one to deliver the switching stations and substation upgrades.
The Hunter Transmission Project is expected to support an average of up to 210 direct jobs per year during construction, and 140 ongoing operational jobs from 2030.
The project will also create additional demand for workers in local manufacturing, retail, transport and the supply of goods and services.
A guiding project principle is Hunter-first. This means where possible we create opportunities to build on the Hunter region’s diverse economic skill base and grow local jobs as we plan and build the Hunter Transmission Project.
We signed a commitment deed with Transgrid as the preferred network operator and shortlisted 7 contractors to participate in the tender phase for construction of the Hunter Transmission Project
We invited local businesses to express their interest to work with the Hunter Transmission Project. Tenderers are assessed on their commitment to using local goods and services. Shape
Related content
Learn about how we're working with the community
Learn about the project's environmental impact statement
View resources and information about the Hunter Transmission Project
Learn how we're working with affected landowners
Get in touch with the Hunter Transmission Project community team
Send the local HTP community team an email at [email protected]
Phone us on 1800 645 972 (9am to 5pm, Monday to Friday)
Get in touch with EnergyCo
1800 118 894 (9am to 5pm, Monday to Friday)
Sign up for our Powering NSW e-newsletter.