A NSW Government website

Central-West Orana Transmission Project

Commonwealth planning approval granted for REZ transmission project

The Central-West Orana REZ transmission project has now secured Commonwealth planning approval. This achievement moves the project into the delivery phase and is a significant step forward in Australia’s renewable energy future. 

Learn more about this milestone in the media release. 

About the transmission project

The Central-West Orana Renewable Energy Zone (REZ) will be serviced by new transmission network infrastructure, including transmission lines and energy hubs, which will transfer power generated by solar and wind farms to electricity consumers. This infrastructure will be critical for the successful operation of the REZ. EnergyCo is leading the development of the REZ transmission network infrastructure as the Infrastructure Planner for the REZs in NSW.

EnergyCo is responsible for developing and overseeing the planning and approval processes for the REZ network infrastructure. After a competitive tender process, EnergyCo entered into a commitment deed with a consortium comprised of ACCIONA, COBRA and Endeavour Energy (ACEREZ) as preferred network operator for the REZ. ACEREZ has signed on to seek approval to design, build, finance, operate and maintain the REZ transmission network.

To support the delivery of the transmission network infrastructure and the REZ as a whole, we are working closely with the developers of renewable energy projects to plan their connections into the network. We are also working with generators and other key stakeholders to develop strategies to manage cumulative impacts within the REZ and deliver community benefit initiatives.

Planning approvals

The Central-West Orana REZ transmission project has reached a significant milestone, securing State planning approval in June 2024 and Commonwealth planning approval in August 2024. This marks the first time a REZ in Australia has achieved this critical step under the NSW Electricity Infrastructure Roadmap. The project will deliver at least 4.5 gigawatts (GW) of transmitted electricity.

Planning approval follows detailed technical planning and extensive community consultation. The Environmental Impact Statement (EIS) was exhibited from late September until early November 2023 and included measures to avoid, minimise or mitigate potential environmental and community impacts. Community feedback informed a number of key changes to the project, which are described and assessed in an Amendment Report.

The project has been declared a Critical State Significant Infrastructure (CSSI) project by the Minister for Planning. Under the NSW Environment Planning and Assessment Act 1979, all CSSI applications are required to go through a comprehensive environmental assessment process.

View the REZ transmission project on the NSW Planning Portal

EnergyCo and the preferred network operator for the project, ACEREZ, are now requesting administrative modifications to the approval conditions issued by the Department of Planning, Housing and Infrastructure for the Central-West Orana Transmission Project (SSI 48323210). 

These administrative modifications are intended to improve clarity and make compliance obligations clearer to ensure the project can proceed efficiently and without delay. They do not in any way reduce our obligations to safeguard safety, heritage, biodiversity or managing impacts such as noise under the project, nor do they change the size or footprint of the project.

Next steps

EnergyCo will continue working with the community, impacted landowners, government agencies and other stakeholders to keep people informed of project progress. 

We will now award the final contract with the network operator and achieve financial close, scheduled for the second half of 2024. Construction works are expected from late 2024, with initial operation anticipated in 2028.

Working with industry

New work packages for constructing transmission lines in the Central-West Orana REZ were made available in July 2024 with more planned over the next year for tender opportunities across various categories.

Industry briefings were held between 29 July and 6 August and opened to local and Aboriginal businesses looking for opportunities to participate in the energy transition.  These forums were an opportunity for businesses to learn about upcoming tender opportunities, scope of works, training, business support and resources.  

EnergyCo delivered these forums in partnership with preferred network operator, ACEREZ, a consortium of ACCIONA, COBRA and Endeavour Energy. Close to 300 people attended the 11 forums that were delivered across six locations in the Central-West Orana region including Wellington, Dubbo, Mudgee, Coolah, Cassilis and Dunedoo.   

cwo-rez-eis-image-2

A significant milestone has been reached with the Central-West Orana REZ transmission project securing planning approval.

cwo-rez-drone-dubbo

EnergyCo is developing a program to deliver tangible benefits for the community.

cwo-rez-eis-image-1

The Environmental Impact Statement was exhibited from late September until early November 2023 on the NSW Planning Portal.

cwo-rez-eis-image-3

The Response to Submissions and Amendment reports have been published on the NSW Planning Portal.

Contact us

If you have any questions about the Central-West Orana REZ or would like to provide feedback, please contact us at any time:

Email: [email protected]

Tel: 1800 032 101 (9am to 5pm, Monday to Friday)